A courthouse renovation has two schedules to consider: the construction schedule and the daily work of the people using the building. Court proceedings, public visits and staff responsibilities all belong in the planning conversation.

The Macon-Bibb Courthouse improvement documents make that relationship explicit. The county’s October 2025 addendum calls for the building to remain occupied while the individual spaces being renovated are unoccupied. It also requires coordination with court services and continued access to areas still conducting business.
Explore the courthouse block
601 Mulberry Street, Macon, GA 31201
Satellite view of the working courthouse and its downtown setting. Imagery is for location reference and may predate current construction.
For an owner preparing a similar project, the following questions can help turn operational needs into a practical discussion with the design and construction team.
Map the building as people use it
Start with an ordinary working day. Where do visitors arrive? Which offices receive the most traffic? Where do employees move between departments? Mark these activities on a floor plan alongside the proposed construction areas.
Include the people who manage the building and those who use it daily. A route that looks convenient on a drawing may overlap with a waiting area, scheduled proceeding or essential staff function.
Define each phase beyond the work itself
A phase needs more than a start and finish date. Discuss which rooms will be available, which functions must move, what needs to happen before construction begins and what must be ready before the next area is released.
For Macon-Bibb, the published requirements assign the county responsibility for moving loose furnishings and files from renovation spaces. That is a useful reminder to give owner activities their own place in the schedule.
Plan deliveries and access together
The courthouse addendum addresses worker identification, deliveries, parking, building entry and movement to work areas. Owners should bring the appropriate operational and security representatives into these discussions early, then establish how changes will be communicated.
Agree on how disruption is handled
Ask which activities could affect nearby operations and how advance notice will work. Identify one owner contact for scheduling decisions and a clear route for reporting a problem. The county’s documents specifically require coordination around work that could disrupt court proceedings.
Plan the return to use
Before releasing a renovated area, discuss cleaning, inspections, equipment orientation, furniture moves and updated directions for staff and visitors. These tasks need time and named responsibilities, just as the construction work does.
Explore Warren Associates’ Bibb County Courthouse portfolio and construction services, or contact our team to discuss a renovation in an occupied building.
Project reference: Macon-Bibb Courthouse Addendum 1, October 29, 2025. The planning questions above are general owner guidance; the cited requirements describe this specific county project.